Data centers in Iowa

Every site we track in Iowa, the jobs each one brings where a public source states them and the officials who represent them.

More: See Iowa on the map · What changed near you · Iowa officials · Filter all Iowa sites

Count89sites tracked (52 operating, 9 under construction, 28 announced)
Single-site maximum1,300largest sourced construction figure at one site (1 site sourced; not added up)
Sum of 4 sitesat least 492permanent jobs committed or forecast at 4 sites, not yet confirmed as filled
Single site$2.5 billionannounced investment at 1 site
What changed after November 3

Election Day was Nov 3, 2026. These are winners of AP-called races who take office in January 2027. Each links to its AP race call. This box covers races for governor, U.S. Senate and U.S. House only. Other statewide offices, such as lieutenant governor, are not included. Results are unofficial until Iowa certifies them.

  • Rob Sand (D), Governor-elect. Called by AP. source
  • Josh Turek (D), U.S. Senator-elect. Called by AP. source
  • Sarah Trone Garriott (D), U.S. Representative-elect, IA-3. Called by AP. source
  • Lindsay James (D), U.S. Representative-elect, IA-2. Called by AP. source
  • Chris McGowan (R), U.S. Representative-elect, IA-4. Called by AP. source
  • Christina Bohannan (D), U.S. Representative-elect, IA-1. Called by AP. source

Sites in Iowa

Sites with sourced job numbers first. Construction and permanent jobs are shown separately and never added together.

SiteCountyStatusConstruction jobsPermanent jobs
Meta Altoona Data Center Campus
Meta
PolkOperating1,300more than 400
Google Cedar Rapids Data Center Campus
Google
LinnUnder constructionnot stated31
Google Council Bluffs Data Center
Google
PottawattamieOperatingnot stated31
QTS Cedar Rapids Data Center Campus
QTS Data Centers
LinnUnder constructionnot statedat least 30
713 Nebraska Carrier Hotel (FiberComm)
ImOn Communications (formerly FiberComm)
WoodburyOperatingnot statednot stated
Apple Waukee Data Center
Apple
DallasOperatingnot statednot stated
Applied Digital Adair County Data Center
Applied Digital
AdairAnnouncednot statednot stated
Ark Data Centers Marion (Cedar Rapids)
Ark Data Centers (formerly Involta)
LinnOperatingnot statednot stated
Aureon 616 Data Center
Aureon
PolkOperatingnot statednot stated
Aurum Elk Data Center Project (Central City)
Aurum Capital Ventures
LinnAnnouncednot statednot stated
Bluebird Quad Cities Data Center
Bluebird Network
ScottOperatingnot statednot stated
Burlington Hill AI Data Center (Fort Madison)
Octopus Investments, LLC
LeeAnnouncednot statednot stated
COPT Defense Van Meter Data Center Shell Site
COPT Defense Properties
DallasAnnouncednot statednot stated
Cologix DSM1 (Financial Center)
Cologix
PolkOperatingnot statednot stated
Cologix DSM2 (Cedar Falls)
Cologix
Black HawkOperatingnot statednot stated
Cologix DSM3 Altoona
Cologix
PolkAnnouncednot statednot stated
Connect Des Moines
Owner not yet confirmed
Operatingnot statednot stated
CyrusOne OCB1 Council Bluffs Data Center
CyrusOne
PottawattamieOperatingnot statednot stated
DartPoints North Liberty Edge Data Center
DartPoints
JohnsonOperatingnot statednot stated
Edged Ankeny (Des Moines) Data Center
Edged Energy
PolkUnder constructionnot statednot stated
Show all 89 sites
SiteCountyStatusConstruction jobsPermanent jobs
Edged Council Bluffs Data Center Campus (Project Lola)
Edged Energy
PottawattamieUnder constructionnot statednot stated
Edged DSM01-1 Data Center
Owner not yet confirmed
PolkUnder constructionnot statednot stated
Energy Conversion Group Coon Rapids Bitcoin Mine
Energy Conversion Group (ECG)
CarrollOperatingnot statednot stated
Enseva Cedar Rapids
Owner not yet confirmed
Operatingnot statednot stated
Enseva Hiawatha Data Center
Enseva
LinnOperatingnot statednot stated
Facebook Altoona Data Center 2
Meta
PolkOperatingnot statednot stated
Fidium Des Moines Data Center
Fidium (Consolidated Communications)
PolkOperatingnot statednot stated
ForceAmp.com
Owner not yet confirmed
JohnsonOperatingnot statednot stated
GABLE CORP
Owner not yet confirmed
PottawattamieOperatingnot statednot stated
Geneseo Communications Inc
Owner not yet confirmed
ScottOperatingnot statednot stated
Global Reach Ames Data Center
Global Reach Internet Productions
StoryOperatingnot statednot stated
Google Palo Data Center Campus
Google
LinnAnnouncednot statednot stated
Great Lakes Colocation Data Center
Great Lakes Communication
DickinsonOperatingnot statednot stated
Heartland Technology Data Center (HTDC)
Heartland Technology (JDC Data LLC)
BuchananOperatingnot statednot stated
IP Pathways DSM1
Owner not yet confirmed
Operatingnot statednot stated
IP Pathways Urbandale Data Center
IP Pathways
PolkOperatingnot statednot stated
ITS Iowa Data Center (Monticello)
Infrastructure Technology Solutions (ITS)
JonesOperatingnot statednot stated
InfoBunker Underground Data Center
InfoBunker, LLC
BooneOperatingnot statednot stated
Karis Dubuque County Data Center
Karis
DubuqueAnnouncednot statednot stated
Karis Peosta Data Center Site (south of U.S. 20)
Karis
DubuqueAnnouncednot statednot stated
LightEdge Altoona Data Center Campus
LightEdge Solutions
PolkOperatingnot statednot stated
LightEdge Ames Edge Colocation Data Center
LightEdge Solutions
StoryAnnouncednot statednot stated
LightEdge Boone Colocation Data Center
LightEdge Solutions
BooneAnnouncednot statednot stated
Lightedge Des Moines 1
Owner not yet confirmed
PolkOperatingnot statednot stated
Lightedge Des Moines 2
Owner not yet confirmed
PolkOperatingnot statednot stated
Long Lines Secure Data Center
Long Lines
WoodburyOperatingnot statednot stated
Lumen Pleasant Hill Data Center
Lumen
PolkOperatingnot statednot stated
Mason City South Side Data Center Site (43rd Street SW)
Undisclosed developer
Cerro GordoAnnouncednot statednot stated
Meta Davenport Data Center
Meta
ScottAnnouncednot statednot stated
Microsoft Project Alluvion Data Center
Microsoft
PolkOperatingnot statednot stated
Microsoft Project Ginger East Data Center
Microsoft
PolkUnder constructionnot statednot stated
Microsoft Project Ginger West Data Center
Microsoft
PolkUnder constructionnot statednot stated
Microsoft Project Mountain Data Center
Microsoft
DallasOperatingnot statednot stated
Microsoft Project Osmium Data Center
Microsoft
WarrenUnder constructionnot statednot stated
Microsoft Project Ruthenium Data Center
Microsoft
MadisonAnnouncednot statednot stated
Microsoft Van Meter Data Center (Vision Park)
Microsoft
DallasAnnouncednot statednot stated
Microsoft West Des Moines
Microsoft
PolkOperatingnot statednot stated
Microsoft Woodward Data Center Campus
Microsoft
DallasAnnouncednot statednot stated
MiningStore Eldora Township Site
MiningStore
HardinAnnouncednot statednot stated
MiningStore St. Anthony Site
MiningStore
MarshallOperatingnot statednot stated
MiningStore Union Township Site
MiningStore
HardinAnnouncednot statednot stated
Oppidan Cedar Rapids Data Center
Oppidan
LinnAnnouncednot statednot stated
Oppidan Des Moines Data Center
Oppidan
PolkOperatingnot statednot stated
PathOne Ida County Data Center (Galva site)
PathOne Data Centers
IdaAnnouncednot statednot stated
PathOne Sioux County Data Center (Hull)
PathOne Data Centers
SiouxAnnouncednot statednot stated
Project West
Tract
WarrenAnnouncednot statednot stated
QTS Clinton Data Center Campus
QTS Data Centers
ClintonAnnouncednot statednot stated
QTS Fairfax Data Center
Owner not yet confirmed
LinnUnder constructionnot statednot stated
Router12 Brick and Tile Colocation (Mason City)
Router12 Networks LLC
Cerro GordoOperatingnot statednot stated
SFN IA-Davenport
Owner not yet confirmed
Operatingnot statednot stated
SFN IA-Emery
Owner not yet confirmed
Operatingnot statednot stated
SFN IA-IowaFalls
Owner not yet confirmed
Operatingnot statednot stated
SFN IA-Urbana
Owner not yet confirmed
Operatingnot statednot stated
SFN IA-Waterloo
Owner not yet confirmed
Operatingnot statednot stated
Salix Data Center Site (Midwest Capital Group)
Midwest Capital Group (MidAmerican Energy)
WoodburyAnnouncednot statednot stated
Simple Mining Cascade (Dubuque County)
Simple Mining
DubuqueAnnouncednot statednot stated
Simple Mining Manchester
Simple Mining
DelawareAnnouncednot statednot stated
South Front Networks IA-Davenport Interconnection Facility
South Front Networks
ScottOperatingnot statednot stated
South Front Networks IA-Emery
South Front Networks
Cerro GordoOperatingnot statednot stated
South Front Networks IA-Waterloo
South Front Networks
Black HawkOperatingnot statednot stated
South Spencer Aureon hut
Owner not yet confirmed
Operatingnot statednot stated
Swarm Systems Marshalltown Data Center
Swarm Systems
MarshallAnnouncednot statednot stated
TierPoint Newton Data Center
TierPoint
JasperOperatingnot statednot stated
Tract Altoona Technology Park
Tract
PolkAnnouncednot statednot stated
U.S. Secure Hosting Center (USSHC)
U.S. Secure Hosting Center
JonesOperatingnot statednot stated
US Signal IA01 Des Moines Data Center (Waukee)
US Signal
DallasOperatingnot statednot stated
Uniti Des Moines Data Center (formerly Windstream Wholesale)
Uniti
PolkOperatingnot statednot stated
Wahawk Power Data Center
Wahawk Power, LLC
Black HawkAnnouncednot statednot stated
ark data centers, Cedar Rapids,IA
Owner not yet confirmed
Operatingnot statednot stated

Counties with data center sites

Show all 27 counties
Embed this state card
<iframe src="https://mainstreetmegawatt.com/embed/state/ia.html" width="100%" height="220" style="border:0" loading="lazy" title="Data centers in Iowa"></iframe>

What does this mean for your community?

Electric bills, water, housing and taxes in Data centers in Iowa: sites, jobs and officials: what we know, what remains unknown and who can answer. Statewide figures are context, not forecasts for any one community.

Will my electric bill rise?

No sourced figure yet for this state.

In writing
No modeled or measured estimate of the effect on household bills has been published for this state.
What remains unknown
The effect on household bills in most states.
Who can answer
Your state utility commission and your utility's rate cases.
Ask
Will data centers pay the full cost of the power lines and plants built for them? Where is that written in a rate order?

How much water will it use?

No sourced figure yet for this state.

In writing
No tracked project in this state has a published water figure in our sources.
What remains unknown
Water use for nearly every other project.
Who can answer
Your local water utility and county commission.
Ask
How much water will this project use each day? Where will it come from?

Will housing get more expensive?

No sourced figure yet for this state.

In writing
No public body we found tracks data center effects on local rents or land prices.
What remains unknown
Effects on local land prices, rents and housing.
Who can answer
Local land records and planning commission minutes.
Ask
Has anyone studied what this project will do to local rents and home prices?

What are taxpayers giving up?

Tax increment rebates capped at $1 billion in aggregate over all phases, tied to employment thresholds (city resolution) (QTS Cedar Rapids Data Center Campus).

In writing
1 sourced tax incentive record from state and local filings. See the records
What remains unknown
The full public cost and the net tax revenue for most projects.
Who can answer
Your state economic development agency and county commission.
Ask
What tax breaks does this project get? What must it deliver in return?

What the agreements say

  • QTS Cedar Rapids Data Center Campus: Tax increment rebates capped at $1 billion in aggregate over all phases, tied to employment thresholds (city resolution).

From 1 signed or approved incentive record in our sources for this state. Terms are as published; we have not audited whether commitments were met.

Ask your officials who pays

Your officials in Iowa

Kim Reynolds R

Governor · 89 sites represented
Not on record yet

Chuck Grassley R

U.S. Senator · 89 sites represented
Not on record yet
Call 202-224-3744 · Contact form

Joni Ernst R

U.S. Senator · 89 sites represented
Not on record yet
Call 202-224-3254 · Contact form

Zachary Nunn R

U.S. Representative · IA-3 · 30 sites represented
Not on record yet
Call 202-225-5476

Ashley Hinson R

U.S. Representative · IA-2 · 27 sites represented
Not on record yet
Call 202-225-2911

Randy Feenstra R

U.S. Representative · IA-4 · 18 sites represented
Not on record yet
Call 202-225-4426

Mariannette Miller-Meeks R

U.S. Representative · IA-1 · 14 sites represented
Not on record yet
Call 202-225-6576

Incoming in January 2027

Rob Sand D

Governor-elect · 89 sites represented
Quote

"As governor, I'd want a bill on my desk to make sure these data centers pay their own way, including covering any increase in costs on utilities so that your bills don't go up one cent." source

Josh Turek D

U.S. Senator-elect · 89 sites represented
Quote

"I think one, we need to have no more tax breaks to these corporations. Pay their fair share. Secondly, we need to make sure that these data centers are not driving up the energy rates to the end user." source

Sarah Trone Garriott D

U.S. Representative-elect · IA-3 · 30 sites represented
Paraphrase

Lindsay James D

U.S. Representative-elect · IA-2 · 27 sites represented
Paraphrase

Chris McGowan R

U.S. Representative-elect · IA-4 · 18 sites represented
Quote

"I have said that data centers should pay for all of the infrastructure, and I continue to believe that that is the right course of action." source

Christina Bohannan D

U.S. Representative-elect · IA-1 · 14 sites represented
Paraphrase